Operation and commissioning of conveyors

1. The stationary conveyor must be installed on a fixed base in accordance with the prescribed installation method. Before the mobile conveyor is officially put into operation, the wheels must be delta-locked or braked. To avoid walking on the job when several conveyors are running in parallel, there should be a one-meter walkway between machines and between machines and walls.
2. Before using the conveyor, please check whether the running parts, belt buckles and bearing devices are normal, and whether the safety equipment is complete. The belt tension must be adjusted to the appropriate level before starting work.
3. The conveyor belt should start without load. Wait for normal operation before feeding. It is forbidden to enter the material first and then drive.
4. When multiple conveyors are running in series, they should start from the discharge end and run sequentially. After all normal operation, the material can be fed.
5. When the belt deviates during operation, it should be stopped for adjustment and not used reluctantly, so as not to wear the edge and increase the load.
6. The temperature of the working environment and shipped materials must be no higher than 50 degrees C and no lower than -10 degrees C. Materials with acidic and alkaline oils and organic solvents are not transported.
7. The movement of pedestrians or passengers on the conveyor belt is prohibited.
8. Feeding must be stopped before stopping, and parking can only be stopped when the material on the belt has been unloaded.
9. The conveyor motor must be well insulated. Do not pull or pull the mobile conveyor cable. The motor must be securely grounded.
10. It is strictly forbidden to pull the belt with your hands when the belt slips, in order to avoid accidents.

 

screw conveyor-1


Debugging steps
(1) After installing each equipment, the conveyor is carefully adjusted according to the requirements of the drawing.
(2) Each gearbox and moving parts are filled with appropriate lubricating oil.
(3) After the conveyor installation meets the requirements, each individual equipment is manually tested and combined with the conveyor according to the promotion requirements.
(4) Debugging of the electrical part of the conveyor. Including debugging normal electrical wiring and operation, so that the equipment has good performance and achieves the designed function and condition.

 